This was a full turnkey (EPC) 44kV Steel Monopole Overhead Line (OHL) project and allowed us to showcase our solution-driven capabilities.

The purpose of the project was to replace an existing section of 44kV Line as the existing section of line was in a corroded and poor state overall.

Challenges Faced – design and construct the line within a 5m corridor so as to construct the new line before dismantling the existing corroded 44kV Line.

Highlights – Project was completed 2 weeks ahead of schedule. The project was completed within contract price with no additional costs throughout the project.